Construction Update 7-21 to 8-3
- 5 to 6 bore crews on-site
- Bored 613 feet on Roepke Road (Central Office PON)
- Bored 2,246 feet on M-52 (Central Office PON)
- Bored 344 feet on Island Lake Drive (Island Lake PON)
- Bored 562 feet on Beede Drive / Hill Road (Island Lake PON)
- Bored 140 feet on North Territorial (Island Lake PON)
- Finished boring on Bush Road (Sugarloaf PON)
- Installed 10 pedestals in Central Office PON
- Pulled fiber in Werkner PON
- Worked on splicing fiber in Werkner PON
- Constructed drops at 20 houses in Werkner PON and 8 houses in Island Lake PON
- 5 to 6 bore crews on-site
- Bore on M-52 (Central Office PON)
- Bore on Beeman Road (Sugarloaf PON)
- Bore on Bens Drive (Sugarloaf PON)
- Complete fiber placement and splicing in Werkner PON
Implementation Committee Meeting 8-5-2019
Draft Agenda
LYNDON TOWNSHIP BROADBAND IMPLEMENTATION COMMITTEE MEETING
Lyndon Township Hall – Fire Hall
Monday, August 5, 2019
6:30 pm
Construction Update 7-14 to 7-27
- 6 to 8 bore crews on-site
- Bored 1,343 feet on Roepke Road (Central Office PON)
- Bored 4,209 feet on M-52 (Central Office PON)
- Bored 3,170 feet on Bush Road (Sugarloaf PON)
- Bored 2,423 feet on Cassidy Road (Boyce PON)
- Installed 2 pedestals in Central Office PON and 6 pedestals in Sugarloaf PON
- Continued to escalate delayed and incorrect Miss Dig gas and electric locates that are causing delays in boring and drop construction
- MEC sent out July update
- No new sign-ups
- 5 to 6 bore crews on-site
- Bore on M-52 (Central Office PON)
- Bore on Roepke Road (Central Office PON)
- Bore on Bush Road (Sugarloaf PON)
- Complete cable placement and splicing in Werkner PON
- Construct drops at 32 houses in Werkner and Island Lake PON (Update: 5 drops were completed on July 22 and 6 drops were completed on July 23 in Werkner PON)
MEC July Construction Update
Join the Broadband Revolution 60590 Decatur Rd Cassopolis MI 49031
Construction Update 6-30 to 7-20
Work completed 6/30 through 7/13:
4 to 7 bore crews on-site
Bored 2,044 feet on Island Lake Point (Island Lake PON)
Bored 2,700 feet on North Territorial Road (Island Lake PON)
Bored 800 feet on Rex Road (Island Lake PON)
Bored 593 feet under Island Lake (Island Lake PON)
Bored 1,524 feet on Roepke Road (Central Office PON)
Bored 1,065 feet on South Lake Road (Central Office PON)
Bored 2,614 feet on M-52 (Central Office PON)
Installed 7 pedestals in Island Lake PON and 3 pedestals in Central Office PON
Escalated delayed and incorrect Miss Dig gas and electric locates that are causing delays in boring and drop construction
Beta testers reported that they are happy with the new broadband service
1 new signup (830 total signups: 308 Basic, 279 Ultra, 236 Gig, 4 undecided, 170 with phone, 3 phone only)
Work to be completed 7/14 through 7/20:
6 to 8 bore crews on-site
Bore on Rex Road (Island Lake PON)
Bore on M-52 (Central Office PON)
Bore on Roepke Road (Central Office PON)
Bore on Cassidy Road (Boyce PON)
Bore on Bush Road (Sugarloaf PON)
Construct drops at 32 houses in Werkner and Island Lake PON (postponed from the previous week due to Miss Dig delays and inaccuracies)
Construction Update 6-23 to 7-6
- 5 bore crews on-site
- Spliced into house box, installed router, and activated broadband service at 5 beta testers on Werkner Road
- Bored 1,427 feet on Waterloo Road (Werkner PON)
- Bored 537 feet on Island Lake Drive (Island Lake PON)
- Bored 1,000 feet (estimate) on North Territorial Road (Island Lake PON)
- Bored 994 feet on Roepke Road (Central Office PON)
- Bored 294 feet on Coopersfield Road (Boyce PON)
- Installed 6 pedestals in Werkner PON, 1 pedestal in Boyce PON, and 2 pedestals in Island Lake PON
- Lyndon Township residents received an MEC flyer in their Summer property tax bill
- No new signups
- 5 bore crews on-site
- Bore under Island Lake (Island Lake PON)
- Bore on N. Territorial Road (Island Lake PON)
- Bore on Island Lake Point (Island Lake PON)
- Bore on Rex Road (Island Lake PON)
- Bore on Roepke Road (Central Office PON)
- Construct drops at 32 houses in Werkner and Island Lake PON
Construction Update 6-16 to 6-29
LYNDON DESIGN 110518
- 5 bore crews on-site
- Bored 118 feet on Mester Road (Werkner PON)
- Bored 207 feet on Cooper Ridge Drive / Waterloo Road connector (Werkner PON)
- Bored 520 feet on Island Lake Drive (Island Lake PON)
- Bored 3,310 feet on North Territorial Road (Island Lake PON)
- Bored 477 feet on Roepke Road (Central Office PON)
- Bored 2,294 feet on Coopersfield Road (Boyce PON)
- Installed 1 pedestal in Werkner PON, 5 pedestals in Boyce PON, and 7 pedestals in Island Lake PON
- Hired new splicers
- No new signups
- 5 bore crews on-site
- Finish boring on Cooper Ridge Drive / Waterloo Road Connector (Werkner PON)
- Bore under Island Lake (Island Lake PON)
- Bore on N. Territorial Road (Island Lake PON)
- Bore on Roepke Road (Central Office PON)
- Bore on Coopersfield Road (Boyce PON)
- Splice along Waterloo Road
- Splice into house box, install router, and activate broadband service at 5 beta testers on Werkner Road
MEC – June Construction Update
We “turned up the light” at the Township Hall last week, and now you can get a taste of what’s to come with high-speed fiber internet.
Township official Gary Munce said, “The Lyndon Broadband Implementation Committee believes the activation of reliable, high-speed fiber internet and phone service at the Lyndon Township hall will bring new and exciting opportunities; officials, staff, commissions, residents and visitors will all see benefits. For example, new digital signage will be installed to better inform residents and visitors of upcoming events and information, and internet service will available soon to the new Border to Border trail-head adjacent to the town hall.”
We appreciate everyone who stopped by at our June 13 open house. About 140 people attended one of our Cutting the Cord education sessions, learning how to use fiber internet with streaming services to access the entertainment content you want and need. Based on the popularity of this session, we’ll likely bring it back this fall.
Construction efforts continue at full speed, and we expect to light up our first homes in the next couple of weeks. It’s just a matter of time before everyone in Lyndon Township is streaming at the speed of light.
All MEC Presentations – slides
MEC has made four presentations on topics related to Broadband installation, setup and use.
Each presentation has featured a series of slides. You can find these presentation slides at the links here.
Construction Update 6-2 to 6-15
- 5 to 6 crews on-site
- Bored 660 feet on Mester Road (Werkner PON)
- Bored 1,904 feet on Roe Road (Central Office PON)
- Bored 1,225 feet on Coopersfield Road (Boyce PON)
- Bored 1,156 feet on Island Lake Road (Island Lake PON)
- Bored 289 feet on Waterloo Road (Werkner PON)
- Installed 2 pedestals in Boyce PON and 6 pedestals in Island Lake PON
- 826 total signups (308 Basic, 278 Ultra, 233 Gig, 4 undecided,169 phone, 3 phone only)
- Prepare for the four June 13 “Cutting the Cord” education sessions
- Recorded DNR easement to finish last permit
- 6 crews on-site
- Bore on Cooper Ridge Drive / Waterloo Road Connector (Werkner PON)
- Work on Wildflower Ridge (Werkner PON)
- Bore on Stofer Road (Island Lake PON)
- Bore on Island Lake Drive (Island Lake PON)
- Bore on Mester Road (Island Lake PON)
- Bore on N. Territorial Road (Island Lake PON)
- Bore on Roe Road (Central Office PON)
- Bore on Coopersfield Road (Boyce PON)
- Conduct “Cutting the Cord” education sessions at Township Hall