This website has been created to provide comprehensive, accurate and timely information for residents of Lyndon Township about the broadband network that is being built in the township, If you are looking for information that you do not find here or would like to ask a question, please contact at: Oversight@lyndonbroadband.org.
Project Updates
Construction Update 2-10 to 2-23
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/10 through 2/16: Bored 528 feet on Werkner Road (Werkner PON) Bored 1,367 feet on N Territorial (Island Lake PON) Bored 385 feet on N Territorial (Central Office PON) Note: No boring on February 12 and 13 due to weather 561 […]
MEC Construction Update February
If you have subscribed to Broadband Services you will receive monthly updates from MEC. Here is the February update. The colors of spring are still weeks away, but the colors of construction are popping up all around you as main line construction for your fiber internet service continues. This week crews expect to finish boring […]
Construction Update 2-3 to 2-16
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 2/3 through 2/9: Bored 1,097 feet on Island Lake Road plus set 6 peds and 2 flowerpots Bored 815 feet on Werkner Road plus set 4 peds and 1 tie-in Bored 227 feet on South Drive Bored 1,644 feet on N […]
Broadband Implementation Committee Meeting 2-11-2019
Agenda LYNDON TOWNSHIP BROADBAND IMPLEMENTATION COMMITTEE MEETING Chelsea Senior Center Room 114 512 Washington St, Chelsea, mi Monday, February 11 6:00pm AGENDA
Construction Update January 20-February 9
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/20 through 1/26: Bored 1,008 feet on Island Lake Road (Island Lake PON) Bored 245 feet on Werkner Road (Werkner PON) Submitted WCRC permit application for Waterloo Road (the last one!) Ordered remaining fiber Due to the weather, no boring was […]
**CANCELED** Broadband Implementation Committee Meeting 1-31-2019
This meeting has been canceled due to extreme weather conditions. Updated schedule will be posted here when available. Proposed Agenda LYNDON TOWNSHIP BROADBAND IMPLEMENTATION COMMITTEE MEETING Chelsea Senior Center Room 114 512 Washington St, Chelsea, mi Thursday, January 31, 6:00pm Agenda
Construction Update January 13-26
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/13 through 1/19: Continued boring on Island Lake Road (Island Lake PON) Continued boring on Werkner Road (Werkner PON) Found a residential location in central Lyndon Township for equipment holding Received 24 WCRC permits for 23 roads Beeman Road Westborne Court […]
MEC Monthly Construction Update
Subscribers to the broadband service received a January update from MEC Over the last month, work crews with mini excavators and directional boring equipment have been hard at work as fiber internet construction continues. You’re probably seeing a lot of Miss Dig and proposed route flags and right-of-way markers going up. All great indicators that […]
Construction Update January 7-11
Areas referenced below can be located on this map LYNDON DESIGN 110518 Work completed 1/7 through 1/11: Continued boring on Island Lake Road (Island Lake PON) Continued boring on Werkner Road (Werkner PON) Work to be completed 1/7 through 1/11: Three to four drill crews on-site Continue boring on Island Lake Road (Island Lake PON) […]
Broadband Oversight Committee
Township of Lyndon is seeking residents for the Broadband Oversight Committee. If you are interested please submit a letter of interest and resume to the Township. You may submit your resumes via mail to: Marc Keezer, Supervisor Lyndon Township 17751 N. Territorial Road Chelsea, MI 48118 Or email with attachment to: marckeezer@gmail.com See posting on […]