Marking Flags Available for drop installations

As the number of drops (bringing  fiber cable from the road to your home ) increases,  the township is making white flags available to residents to mark personal facilities (see below).   These flags are available at no cost and can be found on the front porch of the township hall.  The flags are in bundles of 25.  Take what you need and please return them after the drop has been completed at you home.

More About Drops-

When you see flags on your property from the MISS DIG locating process   it is a good time to mark any buried, personal facilities you may have.  Miss Dig will locate public utilities (gas, telephone, electric).  The home owner is responsible for marking/identifying  any personal underground facilities, including but not limited to:  sprinkler systems, propane lines, septic lines, water lines, invisible pet fence, etc.  Marking flags, cones or  spray paint are good ways to do this.

MEC, our Internet service Provider and drop contractor, does not contact people before beginning work on their property, unless you requested that during the sign up process. If you would like a telephone notification, please email internetinfo@teammidwest.com or call  MEC at 800.492.5989.

More information about the drop process ia available at:

LYNDON TWP March Presentation FINAL

Construction Update 9-8 to 9-21

Areas referenced below can be located on this map

Work completed 9/8 through 9/14:

  • 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 2,080 feet on M-52 (Central Office PON)
  • Bored 830 feet on Boyce Road (Boyce PON)
  • Bored 2,122 feet on Osius Road (Sugarloaf PON)
  • Bored 1,037 feet on Chestnut Lane / Hickory Lane (Long Lake PON)
  • Bored 460 feet on Stonehill Drive (Long Lake PON)
  • Bored 2,215 feet on Boyce Road (Ellsworth PON)
  • Bored 360 feet on Farnsworth Road (Ellsworth PON)
  • Pulled 10,496 feet of fiber in Central Office PON
  • Spliced fiber in Central Office PON
  • No new sign-ups (833 total; 308 basic, 278 ultra, 240 gig, 4 undecided, 170 with phone, 3 phone only)
  • 16 new drops in Werkner PON this week (totals to-date: 62 total drops – 44 in Werkner PON and 18 in Island Lake PON)
  • Released Island Lake PON to MEC to begin drops and installations
Work to be completed 9/15 through 9/21:
  • 6 to 7 bore crews on-site plus one fiber pull crew and 1 to 2 splicing crews
  • Bore on M-52 (Central Office PON)
  • Bore on Boyce Road (Boyce and Ellsworth PON)
  • Bore on Osius Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on Roe Road (Central Office PON)
  • Continue to pull and splice fiber in Central Office PON
  • Continue drop installations in Werkner PON

Construction Update 9-1 to 9-14

Areas referenced below can be located on this map

Work completed 9/1 through 9/7:
  • 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 120 feet on M-52 (Boyce PON)
  • Bored 253 feet on N Territorial (Central Office PON)
  • Bored 1,674 feet on Boyce Road (Boyce PON)
  • Bored 1,265 feet on Boyce Road (Ellsworth PON)
  • Bored 1,858 feet on Roe Road (Sugarloaf PON)
  • Bored 1,962 feet on Osius Road (Sugarloaf PON)
  • Pulled 3,070 feet of fiber in the Island Lake PON
  • Continued splicing in Island Lake PON
  • One new sign-up (833 total; 308 basic, 278 ultra, 240 gig, 4 undecided, 170 with phone, 3 phone only)
  • Broadband was lit in two houses this week (16 houses have broadband to-date)
  • No new drops this week (totals to-date: 46 total drops – 28 in Werkner PON and 18 in Island Lake PON)
Work to be completed 9/8 through 9/14:
  • 7 bore crews on-site plus a fiber pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on Boyce Road (Boyce and Ellsworth PON)
  • Bore on Osius Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Begin to pull and splice fiber in Central Office PON
  • Resume drop installations in Werkner and Island Lake PONs
  • Release Island Lake PON to MEC to begin drops and installations

Construction Update 8-25 to 9-7

Areas referenced below can be located on this map
Work completed 8/25 through 8/31:
  • 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew
  • Bored 583 feet on M-52 (Central Office PON)
  • Bored 754 feet on South Lake, Northview and Westview (Central Office PON)
  • Bored 5,848 feet on Boyce Road (Boyce PON)
  • Installed 2 pedestals in Island Lake PON and 6 pedestals in Boyce PON
  • Pulled 7,401 feet of fiber in the Island Lake PON
  • Continued splicing in Island Lake PON
  • No new sign-ups
Work to be completed 9/1 through 9/7:
  • 5 to 6 bore crews on-site plus a fiber pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on South Lake Road (Central Office PON)
  • Bore on Boyce Road (Boyce and Ellsworth PON)
  • Continue to pull and splice fiber in Island Lake PON
  • Test Island Lake PON for drop release

Construction Update 8-11 to 8-31

Areas referenced below can be located on this map
Work completed 8/11 through 8/24:
  • 5 to 6 bore crews on-site plus two fiber pulling crews and one splicing crew
  • Bored 271 feet on M-52 (Central Office PON)
  • Bored 992 feet on Sandhill Pointe (Central Office PON)
  • Bored 1,546 feet on South Lake, Northview and Westview (Central Office PON)
  • Bored 5,461 feet on Boyce Road (Boyce PON)
  • Bored 1,389 feet on M-52 (Boyce PON)
  • Bored 2,150 feet on Roe Road (Sugarloaf PON)
  • Installed 2 pedestals in Central Office PON, 2 pedestals in Sugarloaf PON and 1 pedestal in Boyce PON
  • Pulled 4,321 feet of fiber in the Werkner PON
  • Pulled 8,991 feet of fiber in the Island Lake PON
  • Continue splicing in Island Lake PON
  • Tested and turned over Werkner PON to MEC to begin home installations and activations
  • No new sign-ups
Work to be completed 8/25 through 8/31:
  • 5 to 6 bore crews on-site plus a fiber pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on North Territorial (Central Office PON)
  • Bore on South Lake Drive (Central Office PON)
  • Bore on Boyce Road (Boyce PON)
  • Bore on Roe Road (Sugarloaf PON)
  • Bore on Osius Road (Sugarloaf PON)
  • Continue to pull and splice fiber in Island Lake PON

Construction Update 8-4 to 8-17

Areas referenced below can be located on this map
LYNDON DESIGN 110518


Work completed 8/4 through 8/10:

  • 4 to 7 bore crews on-site
  • Bored 379′ feet on Island Lake Road (Island Lake PON)
  • Bored 700 feet on M-52 (Central Office PON)
  • Bored 160 feet on Roepke Road (Central Office PON)
  • Bored 1,885 feet on Sandhill Pointe (Central Office PON)
  • Bored 710 feet on N. Territorial Road (Central Office PON)
  • Bored 462 feet on Beeman Road (Boyce PON)
  • Bored 1,393 feet on Cassidy Road (Boyce PON)
  • Bored 1,975 feet on Roe Road (Sugarloaf PON)
  • Installed 1 pedestal in Central Office PON and 3 pedestals in Sugarloaf PON
  • Two new sign-ups for a total of 832 (309 Basic, 278 Ultra, 238 Gig, 4 undecided, 164 w phone, 3 phone only)
  • Continuing to have delays with Miss Dig locating utilities.  Also problems with incorrect location of gas lines continue with Miss Dig.
Work to be completed 8/11 through 8/17:
  • 5 to 6 bore crews on-site plus a cable pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on North Territorial (Central Office PON)
  • Bore on Sandhill Pointe (Central Office PON)
  • Bore on South Lake Drive (Central Office PON)
  • Bore on Boyce Road (Boyce PON)
  • Bore on Roe Road (Sugarloaf PON)
  • Test and turnover Werkner PON to MEC to begin home installations and activations

Construction Update 7-28 to 8-10

Areas referenced below can be located on this map
Work completed 7/28 through 8/3:
  • 5 to 6 bore crews  on-site
  • Bored 436 feet on Cooper Ridge / Waterloo Road connector (Werkner PON)
  • Bored 290 feet on M-52 (Central Office PON)
  • Bored 2,605 feet on Beeman Road (Boyce PON)
  • Bored 1,200 feet on Bens Road (Sugarloaf PON)
  • Installed 1 pedestal in Central Office PON and 2 pedestals in Sugarloaf PON
  • Pulled remaining 8,994 feet of fiber in Werkner PON
  • Completed splicing fiber in Werkner PON
  • Constructed drops at 3 houses in Werkner PON and 11 houses in Island Lake PON
  • No new sign-ups
Work to be completed 8/4 through 8/10
  • 5 to 6 bore crews on-site
  • Bore on Island Lake Road (Island Lake PON)
  • Bore on M-52 (Central Office PON)
  • Bore on Sandhill Pointe (Central Office PON)
  • Bore on North Territorial Road (Central Office PON)
  • Bore on Beeman Road (Sugarloaf PON)
  • Test and turnover Werkner PON to MEC to begin home installations and activations
  • Continue to construct drops in Werkner and Island Lake PONs
  • MEC to send out the monthly construction update including an introduction to their installers

Construction Update 7-21 to 8-3

Areas referenced below can be located on this map
Work completed 7/21 through 7/27:
  • 5 to 6 bore crews on-site
  • Bored 613 feet on Roepke Road (Central Office PON)
  • Bored 2,246 feet on M-52 (Central Office PON)
  • Bored 344 feet on Island Lake Drive (Island Lake PON)
  • Bored 562 feet on Beede Drive / Hill Road (Island Lake PON)
  • Bored 140 feet on North Territorial (Island Lake PON)
  • Finished boring on Bush Road (Sugarloaf PON)
  • Installed 10 pedestals in Central Office PON
  • Pulled fiber in Werkner PON
  • Worked on splicing fiber in Werkner PON
  • Constructed drops at 20 houses in Werkner PON and 8 houses in Island Lake PON
Work to be completed 7/28 through 8/3:
  • 5 to 6 bore crews on-site
  • Bore on M-52 (Central Office PON)
  • Bore on Beeman Road (Sugarloaf PON)
  • Bore on Bens Drive (Sugarloaf PON)
  • Complete fiber placement and splicing in Werkner PON

Construction Update 7-14 to 7-27

Areas referenced below can be located on this map
Work completed 7/14 through 7/20:
  • 6 to 8 bore crews on-site
  • Bored 1,343 feet on Roepke Road (Central Office PON)
  • Bored 4,209 feet on M-52 (Central Office PON)
  • Bored 3,170 feet on Bush Road (Sugarloaf PON)
  • Bored 2,423 feet on Cassidy Road (Boyce PON)
  • Installed 2 pedestals in Central Office PON and 6 pedestals in Sugarloaf PON
  • Continued to escalate delayed and incorrect Miss Dig gas and electric locates that are causing delays in boring and drop construction
  • MEC sent out July update
  • No new sign-ups
Work to be completed 7/21 through 7/27:
  • 5 to 6 bore crews on-site
  • Bore on M-52 (Central Office PON)
  • Bore on Roepke Road (Central Office PON)
  • Bore on Bush Road (Sugarloaf PON)
  • Complete cable placement and splicing in Werkner PON
  • Construct drops at 32 houses in Werkner and Island Lake PON (Update:  5 drops were completed on July 22 and 6 drops were completed on July 23 in Werkner PON)