- Worked on H&M pedestal and hand holes tasks not related to fiber placement or splicing (Ellsworth and Joslin PONs)
- Continued to evaluate which contractor to use for Blind Lake crossing (Bruin PON)
- Began to pull fiber along 2.5 mile line on Boyce Road (Boyce PON)
- Spliced 0 home drops (totals to date: 205 spliced – 89 in Werkner PON, 66 in Island Lake PON and 50 in Central Office PON)
- Completed 7 new home self-installations on Roepke Road, Sandhill Pointe and South Lake Road in Central Office PON (totals to date: 185 with broadband – 87 in Werkner PON, 63 in Island Lake PON and 35 in Central Office PON)
- Move forward with next steps for Blind Lake crossing (Bruin PON)
- Continue H&M pedestal and hand hole tasks not related to fiber placement or splicing (Ellsworth and Joslin PONs)
- Complete pulling remainder of fiber on Boyce Road (Boyce PON)
- Begin to pull fiber in Wild Goose PON
- Continue to reconfigure and/or repair splicing and pedestal prep in Central Office (east of M-52) PON
- Continue to splice home drops in Central Office PON
- Work with home owners on viable home self-installations
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (81) complete
Home Installations 40% (35) complete
88 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
127 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 3% (3) complete
114 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation 64% complete
80 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation 16% complete
45 Subscribers
Bruin
Mainline Boring 97% complete (Blind Lake crossing)
52 Subscribers
Joslin
Mainline Boring complete
58 Subscribers
Ellsworth
Mainline Boring 99% complete (Ellsworth Lake Road – pedestal installation and remaining road crossings)
90 Subscribers