Construction Update January 20-February 9

Areas referenced below can be located on this map

Work completed 1/20 through 1/26:
  • Bored 1,008 feet on Island Lake Road (Island Lake PON)
  • Bored 245 feet on Werkner Road (Werkner PON)
  • Submitted WCRC permit application for Waterloo Road (the last one!)
  • Ordered remaining fiber
Due to the weather, no boring was completed between January 27 and February 1.
Work to be completed 2/3 through 2/9:
  • Continue boring on Island Lake Road (Island Lake PON) with 3 crews
  • Last of the fiber to be delivered to Canton warehouse
  • Submit 4 Livingston County Road Commission permit applications (Note: These permit applications will need to be signed by both Lyndon Township and H&M.)
    • Bowdish Road – Jaycox to Worden Road
    • Joslin Lake Road – county line to Barnum Road
    • Barnum Road – Hadley Road to Joslin Lake Road
    • Hadley Road – county line to Barnum Road

 **CANCELED** Broadband Implementation Committee Meeting 1-31-2019

This meeting has been canceled due to extreme weather conditions.  Updated schedule will be posted here when available. 

Proposed Agenda

LYNDON TOWNSHIP BROADBAND IMPLEMENTATION COMMITTEE MEETING
Chelsea Senior Center Room 114
512 Washington St, Chelsea, mi
Thursday,  January 31,
6:00pm

Agenda

Construction Update January 13-26

Areas referenced below can be located on this map

Work completed 1/13 through 1/19:
  • Continued boring on Island Lake Road (Island Lake PON)
  • Continued boring on Werkner Road (Werkner PON)
  • Found a residential location in central Lyndon Township for equipment holding
  • Received 24 WCRC permits for 23 roads
    • Beeman Road
    • Westborne Court
    • Osius Road
    • Oakridge Road
    • Boyce Road
    • Bowdish Road
    • Bush Road
    • Clark Lake Road
    • Lingane Road
    • Gaddis Road
    • Hadley Road
    • Joslin Lake Road (2 permits)
    • Guinan Road
    • Goodband Road
    • Fourth Street
    • First Street
    • Cassidy Road
    • Bartell Road
    • Leeke Road
    • North Lake Road
    • Second Street
    • Watt Road
    • Wild Goose Lake Road
  • Received 3 drain use permits from Washtenaw County Water Resources Commission (waiting for updated version with corrected expiration date)
  • MEC posted the January construction update
  • Residents who have not signed up for service yet received the January postcard
Work to be completed 1/20 through 1/26:
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • Submit WCRC permit application for Waterloo Road (3 WCRC permits remain to be approved – Waterloo Road, Joslin Lake Drive and Roepke Road)

Note:  Due to weather conditions and equipment issues, little boring progress has been made in the past two weeks.

MEC Monthly Construction Update

Subscribers to the broadband service received a January update from MEC


Over the last month, work crews with mini excavators and directional boring equipment have been hard at work as fiber internet construction continues. You’re probably seeing a lot of Miss Dig and proposed route flags and right-of-way markers going up. All great indicators that your fiber internet service is on the way.

Construction of the mainline from Chelsea to the township line is complete and work is underway along Werkner Road and nearby areas that have permitting completed. From mid December to early January, crews staked over 4,000 foot on Boyce Drive, and bored nearly 2,000 feet on Island Lake Road and 3,469 feet on Ellsworth Lake Road.

We know you’re eager! Please continue to encourage your friends, family or neighbors within the township to visit www.teammidwest.com/lyndon and sign up for service before April 30 to take advantage of the free installation.

Construction Update January 7-11

Areas referenced below can be located on this map

Work completed 1/7 through 1/11:
  • Continued boring on Island Lake Road (Island Lake PON)
  • Continued boring on Werkner Road (Werkner PON)
Work to be completed 1/7 through 1/11:
  • Three to four drill crews on-site
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • Place another fiber order
  • Find another holding location for construction equipment (expected to be at a Lyndon Township property owner as opposed to downtown Chelsea)
  • Identify a water source (not Chelsea) for construction crews
  • Submit WCRC permit for Hadley Road

Broadband Oversight Committee

Township of Lyndon is seeking residents for the Broadband Oversight Committee.

If you are interested please submit a letter of interest and resume to the Township.
You may submit your resumes via mail to:

Marc Keezer, Supervisor
Lyndon Township
17751 N. Territorial Road
Chelsea, MI 48118

Or email with attachment to: marckeezer@gmail.com

See posting on Township Web Site

Connections from Main Line to Homes

As you know,  there are many stages to take the project to conclusion.  At each stage we have hired highly qualified firms to carry out the work. This includes Consulting, Engineering, Outside Plant Construction and ISP (Internet Service Provider)
 We are currently in the process of selecting a firm to install the connections to our homes (drops).  We will have this selection process completed in the next few weeks.  Once we have a contractor on board,  we will develop the detailed schedule and process for making these home connections. We expect to begin this work in early spring.
If you have subscribed to the service , you will be receiving monthly updates via email from MEC our ISP.  Updates  are also being posted to lyndonbroadband.org

Construction Updates December 12 – January 11

Areas referenced below can be located on this map
Work completed 12/16 through 1/4:
  • Staked 4,162 feet on Boyce Drive (Boyce PON)
  • Three drill crews on-site
  • Bored 1,952 feet on Island Lake Road (Island Lake PON)
  • Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON)
  • 3 pedestals and 2 handholes placed in Werkner PON
Work to be completed 1/7 through 1/11:
  • Four drill crews on-site
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • No flagging and minimal staking is expected for the week

 

Construction Updates December 15 – January 2

Work completed 12/9 through 12/15:
  • Bored 208 feet at Lyndon Township Hall (Central Office PON)
  • Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON)
  • Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON)
  • Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
Work to be completed 12/16 through 12/22:
  • Continue staking on private roads
  • Three drill crews on-site
  • Begin boring on Island Lake Road (Island Lake PON)
  • Continue boring on Ellsworth Lake Road (Ellsworth PON)
Work to be completed 12/23 through 1/2/2019:
  • No field work planned
  • Work to resume on January 3, 2019