Construction Update 12-11 to 1-4

Areas referenced below can be located on this map
Work completed 12/22 through 12/28:
  • 4 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew (Note: 1/2 day on 12/24 and no work on 12/25.)
  • Bored 460 feet on Waterloo Road (Sugarloaf PON)
  • Bored 240 feet on Maple Drive (Sugarloaf PON)
  • Bored 180 feet on Sugarloaf Lake Road (Guinan PON)
  • Bored 360 feet on Maple Drive (Guinan PON)
  • Bored 1,150 feet on Hadley Road (Bruin PON)
  • Installed 3 pedestals in Sugarloaf PON and 4 pedestals in Guinan PON
  • Pulled 3,696 feet of fiber in Sugarloaf PON
  • Spliced fiber in Boyce PON
  • Completed new drops in Boyce PON this week. Actual totals will be updated next week. (Last week’s totals to-date: 305 total drops – 84 in Werkner PON, 66 in Island Lake PON, 77 in Central Office PON and 78 in Boyce PON)
  • Spliced 0 jobs (totals to-date: 148 spliced – 84 in Werkner PON, 64 in Island Lake PON and 1 in Central Office PON). (Note: Only two splices remain in Werkner and Island Lake PONs.)
  • 0 new home installations (totals to date: 132 with broadband – 79 in Werkner PON, 52 in Island Lake PON, and 1 in Central Office PON (Township Hall)).  (Note:  No home installations have been scheduled by home owners during the holiday weeks.  Home installations resume on January 7.)
Work to be completed 12/29 through 1/4:
  • 5 to 6 bore crews on-site plus one fiber pull crew and one splicing crew (Note: No work on 12/31/2019 or 1/1/2020.)
  • Bore on Sugarloaf Lake Road (Sugarloaf PON)
  • Bore on Crescent Drive (Bruin PON)
  • Bore on Hadley Road (Bruin PON)
  • Bore on Joslin Lake Road (Bruin PON)
  • Bore on Gregory Court (Bruin PON)
  • Continue to install remaining drops in Werkner, Island Lake, Central Office, and Boyce PONs until ground freezes
  • Continue to pull fiber in Sugarloaf PON and splice fiber in Boyce PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 96% (84) complete
Home Installations 90% (79) complete
88 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (66) complete
Home Installations 74% (52) complete
70 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 88% (77) complete
Home Installations 1% (1) complete
88 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 63% (78) complete
123 Subscribers

Sugarloaf
Mainline Boring 99% complete
Mainline Fiber Installation 84% complete
114 Subscribers

Guinan
Mainline Boring 80% complete
40 Subscribers  

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring 75% complete
Mainline Fiber Installation 24% complete
45 Subscribers

Bruin
Mainline Boring 34% complete
52 Subscribers

Construction Update 12-15 to 12-28

Areas referenced below can be located on this map
Work completed 12/15 through 12/21:
  • 6 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 1,324 feet on Waterloo Road (Sugarloaf PON)
  • Bored 987 feet on Maple Road (Sugarloaf PON)
  • Bored 270 feet on Sugarloaf Lake Road (Guinan PON)
  • Bored 776 feet on Stofer Road (Wild Goose PON)
  • Bored 3,156 feet on Hadley Road (Bruin PON)
  • Bored 616 feet on Goodband Road (Bruin PON)
  • Bored 2,367 feet on Crescent Drive (Bruin PON)
  • Installed 2 pedestals in Sugarloaf PON
  • Pulled 11,550 feet of fiber in Sugarloaf PON
  • Spliced fiber in Boyce and Sugarloaf PONs
  • Released Central Office PON to MEC
  • 0 new drops this week (totals to-date: 305 total drops – 84 in Werkner PON, 66 in Island Lake PON, 77 in Central Office PON and 78 in Boyce PON)
  • Spliced 1 jobs (totals to-date: 148 spliced – 84 in Werkner PON, 64 in Island Lake PON and 1 in Central Office PON)
  • 9 new home installations (totals to date: 132 with broadband – 79 in Werkner PON, 52 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 12/22 through 12/28:
  • 4 to 7 bore crews on-site plus one fiber pull crew and one splicing crew (Note: no work on 12/25 and half day on 12/24)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on Sugarloaf Lake Road (Sugarloaf PON)
  • Bore on Watt Road (Wild Goose PON)
  • Bore on Crescent Drive (Bruin PON)
  • Bore on Hadley Road (Bruin PON)
  • Continue drops in Boyce PON (Note: With this week’s thaw, drops were able to be restarted.  Drops will continue until the ground refreezes.)
  • Continue to pull fiber in Sugarloaf PON and splice fiber in Boyce PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 96% (84) complete
Home Installations 90% (79) complete
88 (up from 84) Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (66) complete
Home Installations 74% (52) complete
70 (up from 68) Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 88% (77) complete
Home Installations 1% (1) complete
88 (up from 79) Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 63% (78) complete
123 Subscribers

Sugarloaf
Mainline Boring 98% complete
Mainline Fiber Installation 72% complete
114 Subscribers

Guinan
Mainline Boring 72% complete
40 Subscribers  

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring 75% complete
Mainline Fiber Installation 24% complete
45 Subscribers

Bruin
Mainline Boring 32% complete
52 Subscribers

Construction Update 12-8 to 12-21

Areas referenced below can be located on this map
Work completed 12/8 through 12/14:
  • 6 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 1,225 feet on Waterloo Road (Sugarloaf PON)
  • Bored 430 feet on Maple Road (Sugarloaf PON)
  • Bored 608 feet on Stofer Road (Wild Goose PON)
  • Bored 1,114 feet on Hadley Road (Wild Goose PON)
  • Bored 297 feet on First Street (Wild Goose PON)
  • Bored 45 feet on Wild Goose Lake Road (Wild Goose PON)
  • Bored 740 feet on Hadley Road (Bruin PON)
  • Bored 1,078 feet on Crescent Drive (Bruin PON)
  • Installed 1 pedestal in Wild Goose PON
  • Spliced fiber in Central Office and Boyce PONs
  • 41 new drops this week (totals to-date: 305 total drops – 84 in Werkner PON, 66 in Island Lake PON, 77 in Central Office PON and 78 in Boyce PON)
  • Spliced 9 jobs (totals to-date: 148 spliced – 84 in Werkner PON, 63 in Island Lake PON and 1 in Central Office PON)
  • 15 new home installations (totals to date: 123 with broadband – 75 in Werkner PON, 47 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 12/15 through 12/21:
  • 6 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on Maple Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on Sugarloaf Lake Road (Sugarloaf PON)
  • Bore on Stofer Road (Wild Goose PON)
  • Bore on Hidden Lake Road (Wild Goose PON)
  • Bore on Watt Road (Wild Goose PON)
  • Bore on Crescent Drive (Bruin PON)
  • Bore on Hadley Road (Bruin PON)
  • Release Central Office PON to MEC for splicing and home installations
  • Continue to pull fiber in Sugarloaf and Long Lake PONs and splice fiber in Central Office and Boyce PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 96% (84) complete
Home Installations 85% (75) complete
88 (up from 84) Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (66) complete
Home Installations 67% (47) complete
70 (up from 68) Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 88% (77) complete
Home Installations 1% (1) complete
88 (up from 79) Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 63% (78) complete
123 Subscribers

Sugarloaf
Mainline Boring 93% complete
Mainline Fiber Installation 35% complete
114 Subscribers

Guinan
Mainline Boring 68% complete
40 Subscribers  

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring 74% complete
Mainline Fiber Installation 24% complete
45 Subscribers

Bruin
Mainline Boring 17% complete
52 Subscribers

Construction Update 12-1 to 12-14

Areas referenced below can be located on this map
 
Work completed 12/1 through 12/7:
  • 7 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 309 feet on Sugarloaf Lake Road (Sugarloaf PON)
  • Bored 30 feet on Waterloo Road (Sugarloaf PON)
  • Bored 600 feet on N Territorial Road (Wild Goose PON)
  • Bored 1,000 feet on Stofer Road (Wild Goose PON)
  • Bored 2,992 feet on Hadley Road (Wild Goose PON)
  • Bored 928 feet on First Street (Wild Goose PON)
  • Bored 2,031 feet on Hadley Road (Bruin PON)
  • Bored 3,082 feet on Bartell Road (Bruin PON)
  • Bored 1,070 feet on M-52 (Long Lake PON)
  • Bored 3,702 feet on Guinan Road (Guinan PON)
  • Bored 795 feet on Sugarloaf Lake Road (Guinan PON)
  • Installed 1 pedestal in Sugarloaf PON, 7 pedestals in Wild Goose PON, and 9 pedestals in Guinan PON
  • Pulled 7,006 feet of fiber in Central Office PON
  • Spliced fiber in Central Office and Boyce PONs
  • 9 new drops this week (totals to-date: 264 total drops – 82 in Werkner PON, 66 in Island Lake PON, 77 in Central Office PON and 39 in Boyce PON)
  • Spliced 7 jobs (totals to-date: 139 spliced – 81 in Werkner PON, 57 in Island Lake PON and 1 in Central Office PON)
  • 0 new home installations (totals to date: 108 with broadband – 70 in Werkner PON, 37 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 12/8 through 12/14:
  • 4 to 7 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on Maple Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on North Territorial (Wild Goose PON)
  • Bore on Stofer Road (Wild Goose PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Hidden Lake Road (Wild Goose PON)
  • Bore on Watt Road (Wild Goose PON)
  • Bore on Crescent Drive (Bruin PON)
  • Continue to pull fiber in Sugarloaf and Long Lake PONs and finish splicing fiber in Sugarloaf PON
  • Continue drop installations in Werkner, Island Lake, Central Office, and Boyce PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 83% (70) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (66) complete
Home Installations 54% (37) complete
68 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 97% (77) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 32% (39) complete
123 Subscribers

Sugarloaf
Mainline Boring 92% complete
Mainline Fiber Installation 26% complete
114 Subscribers

Guinan
Mainline Boring 68% complete
40 Subscribers  

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 41% complete
80 Subscribers

Wild Goose
Mainline Boring 74% complete
Mainline Fiber Installation 21% complete
45 Subscribers

Bruin
Mainline Boring 13% complete
52 Subscribers

Construction Update 11-24 to 12-7

Areas referenced below can be located on this map

Work completed 11/24 through 11/30:
  • 7 bore crews on-site plus one fiber pulling crew and one splicing crew (only 3 days on-site due to Thanksgiving holiday)
  • Bored 75 feet on Cedar Street (Sugarloaf PON)
  • Bored  550 feet on N Territorial Road (Wild Goose PON)
  • Bored 500 feet on Plourde Circle (Wild Goose PON)
  • Bored 530 feet on M-52 (Central Office PON)
  • Spliced fiber in Central Office and Boyce PONs
  • 30 new drops this week (totals to-date: 255 total drops – 82 in Werkner PON, 60 in Island Lake PON, 77 in Central Office PON and 36 in Boyce PON)
  • Spliced 0 jobs (totals to-date: 132 spliced – 81 in Werkner PON, 50 in Island Lake PON and 1 in Central Office PON)
  • 0 new home installations (totals to date: 108 with broadband – 70 in Werkner PON, 37 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 12/1 through 12/7:
  • 7 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on Cedar Drive (Sugarloaf PON)
  • Bore on Sugarloaf Lake Road (Sugarloaf PON)
  • Bore on M-52 (Central Office PON)
  • Bore on North Territorial (Wild Goose PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Wild Goose Lake Road (Wild Goose PON)
  • Bore on First Street (Wild Goose PON)
  • Bore on Bartell Road (Bruin PON)
  • Continue to pull fiber in Sugarloaf and Long Lake PONs and finish splicing fiber in Central Office PON
  • Continue drop installations in Werkner, Island Lake, Central Office, and Boyce PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 83% (70) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 88% (60) complete
Home Installations 54% (37) complete
68 Subscribers

Central Office
Mainline Boring 99% complete
Mainline Fiber Installation 88% complete
Drop Installations 97% (77) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations 29% (36) complete
123 Subscribers

Sugarloaf
Mainline Boring 91% complete
Mainline Fiber Installation 26% complete
114 Subscribers

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 41% complete
80 Subscribers

Wild Goose
Mainline Boring 61% complete
Mainline Fiber Installation 21% complete
45 Subscribers

Construction Update 11-17 to 11-30

Areas referenced below can be located on this map

Work completed 11/17 through 11/23:
  • 6 to 8 bore crews on-site plus one fiber pulling crew and one splicing crew.
  • Bored 634 feet on Cedar Drive (Sugarloaf PON)
  • Bored 850 feet on N Territorial Road (Wild Goose PON)
  • Bored 6,744 feet on Hadley Road (Wild Goose PON)
  • Bored 209 feet on 4th Street (Wild Goose PON)
  • Bored 367 feet on 2nd Street (Wild Goose PON)
  • Bored 1,439 feet on Wild Goose Lake Road (Wild Goose PON)
  • Pulled 5,130 feet of fiber in Sugarloaf PON and 5,416 feet of fiber in Long Lake PON
  • Spliced fiber in Central Office and Boyce PONs
  • 28 new drops this week (totals to-date: 225 total drops – 82 in Werkner PON, 56 in Island Lake PON, 67 in Central Office PON and 20 in Boyce PON)
  • Spliced 0 jobs (totals to-date: 132 spliced – 81 in Werkner PON, 50 in Island Lake PON and 1 in Central Office PON)
  • 22 new home installations (totals to date: 108 with broadband – 70 in Werkner PON, 37 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 11/24 through 11/30 (3 days only due to the Thanksgiving holiday):
  • 7 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on Cedar Drive (Sugarloaf PON)
  • Bore on Sugarloaf Lake Road (Sugarloaf PON)
  • Bore on M-52 (Long Lake PON)
  • Bore on North Territorial (Wild Goose PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Wild Goose Lake Road (Wild Goose PON)
  • Bore on First Street (Wild Goose PON)
  • Bore on Bartell Road (Bruin PON)
  • Continue to pull fiber in Sugarloaf and Long Lake PONs and splice fiber in Central Office PON
  • Continue drop installations in Werkner, Island Lake, Central Office, and Boyce PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 83% (70) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 82% (56) complete
Home Installations 54% (37) complete
68 Subscribers

Central Office
Mainline Boring 98% complete
Mainline Fiber Installation 88% complete
Drop Installations 85% (67) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 95% complete
Drop Installations 16% (20) complete
123 Subscribers

Sugarloaf
Mainline Boring 91% complete
Mainline Fiber Installation 26% complete
114 Subscribers

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 41% complete
80 Subscribers

Wild Goose
Mainline Boring 57% complete
Mainline Fiber Installation 21% complete
45 Subscribers

Construction Update 11-10 to 11-23

Areas referenced below can be located on this map

Work completed 11/10 through 11/16:
  • 6 bore crews on-site plus one fiber pulling crew and one splicing crew.  Note: Minimal work on 11/11 and 11/12 due to the snowy and hazardous conditions.
  • Bored 4,037 feet on Waterloo Road (Sugarloaf PON)
  • Bored 300 feet on N Territorial Road (Wild Goose PON)
  • Installed 20 pedestals in Sugarloaf PON
  • Pulled 6,548 feet of fiber in Long Lake PON
  • Spliced fiber in Central Office and Boyce PONs
  • 18 new drops this week (totals to-date: 197 total drops – 82 in Werkner PON, 55 in Island Lake PON and 60 in Central Office PON)
  • Spliced 6 jobs (totals to-date: 132 spliced – 81 in Werkner PON, 50 in Island Lake PON and 1 in Central Office PON)
  • 8 new home installations (totals to-date: 86 with broadband – 65 in Werkner PON, 20 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 11/17 through 11/23:
  • 6 – 8 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on North Territorial (Sugarloaf and Wild Goose PONs)
  • Bore on Cedar Drive (Sugarloaf PON)
  • Bore on Lingane Road (Long Lake PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Wild Goose Lake Road (Wild Goose PON)
  • Bore on Sugarloaf Lake Road (Guinan PON)
  • Bore on Bartell Road (Bruin PON)
  • Continue to pull fiber in Long Lake PON and splice fiber in Central Office PON
  • Continue drop installations in Werkner, Island Lake and Central Office PONs and start drop installations in Boyce PON
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (82) complete
Home Installations 77% (65) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 81% (55) complete
Home Installations 29% (20) complete
68 Subscribers

Central Office
Mainline Boring 98% complete
Mainline Fiber Installation 73% complete
Drop Installations 76% (60) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers

Sugarloaf
Mainline Boring 89% complete
Mainline Fiber Installation 14% complete
114 Subscribers

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 24% complete
80 Subscribers

Wild Goose
Mainline Boring 29% complete
Mainline Fiber Installation 21% complete
45 Subscribers

Construction Update 11-3 to 11-16

Areas referenced below can be located on this map
Work completed 11/3 through 11/9:
  • 9 to 10 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 385 feet on M-52 (Central Office PON)
  • Bored 170 feet on Cooper Ridge Road (Werkner PON)
  • Bored 579 feet on Gaddis Road (Sugarloaf PON)
  • Bored 1,470 feet on M-52 (Long Lake PON)
  • Bored 2,482 feet on Hadley Road (Wild Goose PON)
  • Bored 2,660 feet on Goodband Road (Wild Goose PON)
  • Bored 570 feet on North Lake Road (Wild Goose PON)
  • Installed 3 pedestals in Wild Goose PON
  • Pulled 200 feet of fiber in Werkner PON and 7,148 feet of fiber in Long Lake PON
  • Spliced fiber in Central Office and Boyce PONs
  • 16 new drops this week (totals to-date: 179 total drops – 80 in Werkner PON, 54 in Island Lake PON and 45 in Central Office PON)
  • Spliced 15 jobs (totals to-date: 111 spliced – 80 in Werkner PON, 45 in Island Lake PON and 1 in Central Office PON)
  • 14 new home installations (totals to-date: 78 with broadband – 63 in Werkner PON, 14 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 11/10 through 11/16:
  • 8 bore crews on-site plus one fiber pull crew and one splicing crew (Note: No work was completed on Monday or Tuesday due to the snowy and hazardous conditions.)
  • Bore on M-52 (Central Office and Long Lake PONs)
  • Bore on Cedar Drive (Sugarloaf PON)
  • Bore on Hadley Road (Long Lake and Wild Goose PONs)
  • Bore on Sugarloaf Lake Road (Guinan PON)
  • Bore on Bartell Road (Bruin PON)
  • Continue to pull and splice fiber in Central Office and Boyce PONs
  • Continue drop installations in Werkner, Island Lake and Central Office PONs
  • Continue home installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (80) complete
Home Installations 75% (63) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 72% (49) complete
Home Installations 21% (14) complete
68 Subscribers

Central Office
Mainline Boring 98% complete
Mainline Fiber Installation 68% complete
Drop Installations 57% (45) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers

Sugarloaf
Mainline Boring 79% complete
Mainline Fiber Installation 14% complete
114 Subscribers

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 3% complete
80 Subscribers

Wild Goose
Mainline Boring 28% complete
Mainline Fiber Installation 21% complete
45 Subscribers

Construction update 10-27 to 11-9

Areas referenced below can be located on this map

Work completed 10/27 through 11/2:
  • 8 to 9 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 370 feet on M-52 (Central Office PON)
  • Bored 264 feet on Cassidy Road (Boyce PON)
  • Bored 3,882 feet on Waterloo Road (Sugarloaf PON)
  • Bored 3,928 feet on M-52 (Long Lake PON)
  • Bored 226 feet on Clark Lake Road (Long Lake PON)
  • Bored 322 feet on Oakdale Road (Long Lake PON)
  • Bored 120 feet on Stonehill Road (Long Lake PON)
  • Pulled 8,602 feet of fiber in Boyce PON
  • Spliced fiber in Central Office and Boyce PONs
  • 26 new drops this week (totals to-date: 163 total drops – 80 in Werkner PON, 49 in Island Lake PON and 34 in Central Office PON)
  • Spliced 2 jobs (totals to-date: 111 spliced – 80 in Werkner PON, 30 in Island Lake PON and 1 in Central Office PON)
  • 7 new home installations (totals to-date: 64 with broadband – 58 in Werkner PON, 5 in Island Lake PON, and 1 in Central Office PON (Township Hall))
Work to be completed 11/3 through 11/9:
  • 9 to 10 bore crews on-site plus one fiber pull crew and one splicing crew
  • Bore on M-52 (Central Office and Long Lake PONs)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Bore on Gaddis Road (Sugarloaf PON)
  • Bore on Roe Road (Sugarloaf PON)
  • Bore on Cedar Drive (Sugarloaf PON)
  • Bore on Goodband Road (Wild Goose PON)
  • Bore on Hadley Road (Wild Goose PON)
  • Bore on Guinan Road (Guinan PON)
  • Continue to pull and splice fiber in Central Office and Boyce PONs
  • Continue drop installations in Werkner and Island Lake PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 95% (80) complete
Home Installations 69% (58) complete
84 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 72% (49) complete
Home Installations 7% (5) complete
68 Subscribers

Central Office
Mainline Boring 97% complete
Mainline Fiber Installation 68% complete
Drop Installations 43% (34) complete
Home Installations 1% (1) complete
79 Subscribers

Boyce
Mainline Boring 99% complete
Mainline Fiber Installation 95% complete
123 Subscribers

Sugarloaf
Mainline Boring 77% complete
Mainline Fiber Installation 14% complete
114 Subscribers

Long Lake
Mainline Boring 91% complete
80 Subscribers