Construction Update 5-31 to 6-13

Areas referenced below can be located on this map
Work completed 5/31/2020 through 6/6/2020:
  • Completed Blind Lake crossing boring
  • Continued splicing in Sugarloaf PON
  • Repaired fiber caused by a squirrel chew resulting in an outage for Lyndon Township and Chelsea School District
  • Continued restoration activities
  • Installed 64 home drops in Sugarloaf, Guinan and Long Lake PONs (totals to date: 521 drops – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 127 in Boyce PON, 83 in Sugarloaf PON, 3 in Guinan PON and 65 in Long Lake PON).
  • Spliced 0 home drops in Boyce PON (totals to date: 361 spliced – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON and 118 in Boyce PON)
  • Completed 31 new home installations in Boyce PON (totals to date: 281 with broadband – 88 in Werkner PON, 64 in Island Lake PON, 64 in Central Office PON and 65 in Boyce PON)
Work to be completed 6/7/2020 through 6/13/2020:
  • Continue restoration activities
  • Pull fiber through Blind Lake crossing
  • Continue splicing in Sugarloaf PON
  • Continue home drops in Long Lake, Sugarloaf Lake and Guinan PONs
  • Continue to splice home drops in Boyce PON
  • Continue home installations in Central Office and Boyce PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  Note: Subscribers per PON has been updated to show increases in new subscriptions.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (89) complete
Home Installations 97% (88) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (67) complete
Home Installations 93% (64) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (87) complete
Home Installations 69% (64) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (127) complete
Home Installations 50% (65)
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 71% (83) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 7% (3) complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 80% (65) complete
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation 97% complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation 47% complete
66 Subscribers

Ellsworth
Mainline Boring complete
91 Subscribers

Construction Update 5-24 t0 6-6

Areas referenced below can be located on this map
Work completed 5/24/2020 through 5/30/2020:
  • Pulled 9,658 feet of fiber in Joslin PON
  • Continued prepping for Blind Lake crossing
  • Continued splicing in Sugarloaf PON
  • Began restoration activities
  • Installed 53 home drops in Sugarloaf and Long Lake PONs (totals to date: 457 drops – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 127 in Boyce PON, 38 in Sugarloaf PON and 49 in Long Lake PON).
  • Spliced 29 home drops in Boyce PON (totals to date: 359 spliced – 89 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON and 116 in Boyce PON)
  • Completed 30 new home installations in Central Office and Boyce PONs (totals to date: 250 with broadband – 87 in Werkner PON, 64 in Island Lake PON, 64 in Central Office PON and 35 in Boyce PON)
Work to be completed 5/31/2020 through 6/6/2020:
  • Continue restoration activities
  • Complete Blind Lake crossing
  • Continue to pull fiber in Joslin PON
  • Continue home drops in Long Lake and Sugarloaf Lake PONs
  • Continue to splice home drops in Boyce PON
  • Continue home installations in Central Office and Boyce PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  Note: Subscribers per PON has been updated to show increases in new subscriptions.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (89) complete
Home Installations 96% (87) complete
91 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (67) complete
Home Installations 93% (64) complete
69 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 94% (87) complete
Home Installations 69% (64) complete
93 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 97% (127) complete
Home Installations 27% (35)
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 33% (38) complete
117 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
41 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 61% (49) complete
81 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation 97% complete
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation 47% complete
66 Subscribers

Ellsworth
Mainline Boring complete
91 Subscribers

Construction Update 5-17 to 5-30

Areas referenced below can be located on this map
Work completed 5/17/2020 through 5/23/2020:
  • Replaced and spliced fiber on Sugarloaf Lake Road in Sugarloaf PON
  • Completed pulling fiber and installing hand holes in Bruin PON – except for Blind Lake crossing
  • Prepped for Blind Lake crossing
  • Began to pull fiber in Joslin PON
  • Continued splicing in Sugarloaf PON
  • Finished splicing drops in Central Office PON
  • Installed 11 home drops (totals to date: 404 drops – 89 in Werkner PON, 67 in Island Lake PON, 86 in Central Office PON, 127 in Boyce PON, 23 in Sugarloaf PON and 12 in Long Lake PON).
  • Spliced 33 home drops (totals to date: 330 spliced – 89 in Werkner PON, 66 in Island Lake PON, 86 in Central Office PON and 89 in Boyce PON)
  • Completed 9 new home installations (totals to date: 220 with broadband – 87 in Werkner PON, 64 in Island Lake PON, 61 in Central Office PON and 8 in Boyce PON)
Work to be completed 5/24/2020 through 5/30/2020:
  • Schedule restoration activities
  • Rescheduled Blind Lake crossing for week of June 1 due to this week’s inclement weather
  • Continue to pull fiber in Joslin PON
  • Continue home drops in Long Lake and Sugarloaf Lake PONs
  • Continue to splice home drops in Boyce PON
  • Continue home installations in Central Office and Boyce PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 96% (64) complete
(Note: Remaining 2 home installations are not ready for service)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 71% (61) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 6% (8)
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 20% (23) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 6% (5) complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
45 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation 97% complete
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring complete
90 Subscribers

Construction Update 5-10 to 5-23

Areas referenced below can be located on this map
Work completed 5/10/2020 through 5/16/2020:
  • Continued H&M pedestal and hand hole tasks not related to fiber placement or splicing (Bruin PON)  
  • Pulled 8,738 feet of fiber and installed hand holes in Bruin PON
  • Completed splicing and testing fiber in Sugarloaf PON
  • Installed 19 home drops (totals to date: 393 drops – 89 in Werkner PON, 67 in Island Lake PON, 86 in Central Office PON, 127 in Boyce PON, 19 in Sugarloaf PON and 5 in Long Lake PON).  Note: There was a miscommunication regarding PON priorities for drops.  Since Long Lake PON has already been marked by Miss Dig, the drops in Long Lake PON will be completed over the next two weeks.  Then drops will be re-started in Sugarloaf PON.  Splicing and home installations in Sugarloaf PON will be done prior to Long Lake PON.
  • Spliced 33 home drops (totals to date: 297 spliced – 89 in Werkner PON, 66 in Island Lake PON, 79 in Central Office PON and 63 in Boyce PON)
  • Completed 10 new home installations (totals to date: 211 with broadband – 87 in Werkner PON, 64 in Island Lake PON, 57 in Central Office PON and 3 in Boyce PON)
Work to be completed 5/17/2020 through 5/23/2020:
  • Continue remaining H&M pedestal and hand hole tasks not related to fiber placement or splicing 
  • Prepare to bore for Blind Lake crossing
  • Replace and splice fiber on Sugarloaf Lake Road
  • Continue to pull fiber and set hand holes in Bruin PON
  • Continue home drops in Long Lake PON
  • Finish splicing home drops in Central Office PON
  • Continue to splice home drops in Boyce PON
  • Continue home installations in Central Office PON
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 96% (64) complete
(Note: Remaining 2 home installations are not ready for service)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (86) complete
Home Installations 66% (57) complete
87 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 2% (3)
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 17% (19) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 6% (5) complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
45 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation 27% complete
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring complete
90 Subscribers

Construction Update 5-3 to 5-16

Areas referenced below can be located on this map

Work completed 5/3/2020 through 5/9/2020:
  • Continued H&M pedestal and hand hole tasks not related to fiber placement or splicing (Joslin and Ellsworth PONs)  
  • Pulled 28,374 feet of fiber in Wild Goose PON
  • Completed major re-splice in Central Office PON cabinet (Note:  Some customers experienced a power outage from 9:00 am to approximately 4:30 pm.)
  • Installed 10 home drops (totals to date: 374 drops – 89 in Werkner PON, 67 in Island Lake PON, 86 in Central Office PON, 127 in Boyce PON and 5 in Sugarloaf PON)
  • Spliced 30 home drops (totals to date: 264 spliced – 89 in Werkner PON, 66 in Island Lake PON, 79 in Central Office PON and 30 in Boyce PON)
  • Completed 12 new home self-installations (totals to date: 201 with broadband – 87 in Werkner PON, 63 in Island Lake PON, 50 in Central Office PON and 1 in Boyce PON)
Work to be completed 5/10/2020 through 5/16/2020:
  • Continue H&M pedestal and hand hole tasks not related to fiber placement or splicing on Edgewater Drive (Bruin PON)
  • Begin to pull fiber and set hand holes in Bruin PON
  • Test fiber in Sugarloaf PON
  • Continue home drops in Sugarloaf PON
  • Finish splicing home drops in Central Office PON
  • Continue to splice home drops in Boyce PON
  • Re-start home installations and continue self-installations
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (86) complete
Home Installations 58% (50) complete
87 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 1% (1)
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 4% (5) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
45 Subscribers

Bruin
Mainline Boring complete
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring complete
90 Subscribers

Construction update 4-26 to 5-9

Areas referenced below can be located on this map

Work completed 4/26/2020 through 5/2/2020:
  • Continued H&M pedestal and hand hole tasks not related to fiber placement or splicing (Bruin PON)
  • Completed reconfiguring and/or repairing splicing and pedestal prep in Boyce PON
  • Completed testing in Boyce PON
  • Completed mainline fiber installation in Long Lake PON.
  • Pulled fiber in Wild Goose PON
  • Spliced 29 home drops in CO PON east of M-52 (totals to date: 234 spliced – 89 in Werkner PON, 66 in Island Lake PON and 79 in Central Office PON)
  • Completed 0 new home self-installations on Roepke Road and South Lake Road in Central Office PON (totals to date: 189 with broadband – 87 in Werkner PON, 63 in Island Lake PON and 39 in Central Office PON)
Work to be completed 5/3/2020 through 5/9/2020:
  • Continue H&M pedestal and hand hole tasks not related to fiber placement or splicing (Bruin, Joslin and Ellsworth PONs)
  • Finish pulling fiber in Wild Goose PON
  • Begin to reconfigure and/or repair splicing and pedestal prep in Sugarloaf PON
  • Complete remaining home drops on South Lake Drive (Central Office PON)
  • Begin home drops in Sugarloaf PON
  • Begin to splice home drops in Boyce PON
  • Conduct major re-splice in Central Office PON cabinet (Note: Planned maintenance outage for some customers on May 6.)
  • Work with home owners on viable home self-installations (Note: MEC to re-start home installations on May 11.)
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (79) complete
Home Installations 45% (39) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 3% (3) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation 100% complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
45 Subscribers

Bruin
Mainline Boring complete
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring complete
90 Subscribers

Construction Update 4-19 to 5-2

Areas referenced below can be located on this map
Work completed 4/19/2020 through 4/25/2020:
  • Identified contractor for Blind Lake crossing (Bruin PON)
  • Completed H&M pedestal and hand hole tasks not related to fiber placement or splicing (Ellsworth and Joslin PONs)
  • Completed reworking and repairing splices in the pedestals east of M-52 (Central Office PON)
  • Began to reconfigure and/or repair splicing and pedestal prep in Boyce PON
  • Completed pulling 2.5 miles of fiber on Boyce Road (Boyce PON)
  • Pulled fiber in Wild Goose PON
  • Spliced 0 home drops (totals to date: 205 spliced – 89 in Werkner PON, 66 in Island Lake PON and 50 in Central Office PON)
  • Completed 4 new home self-installations on Roepke Road and South Lake Road in Central Office PON (totals to date: 189 with broadband – 87 in Werkner PON, 63 in Island Lake PON and 39 in Central Office PON)
Work to be completed 4/26/2020 through 5/2/2020:
  • Schedule contractor and finalize date for Blind Lake crossing (Bruin PON)
  • Continue H&M pedestal and hand hole tasks not related to fiber placement or splicing (Bruin PON)
  • Splice drops in pedestals east of M-52 (Central Office PON)
  • Complete reconfiguring and/or repair splicing and pedestal prep in Boyce PON
  • Pull fiber in Wild Goose and Bruin PONs
  • Continue to splice home drops in Central Office PON
  • Work with home owners on viable home self-installations
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (81) complete
Home Installations 44% (39) complete
88 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 3% (3) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation 25% complete
45 Subscribers

Bruin
Mainline Boring complete
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring complete
90 Subscribers

Construction Update 4-12 to 4-25

Areas referenced below can be located on this map
Work completed 4/12/2020 through 4/18/2020:
  • Worked on H&M pedestal and hand holes tasks not related to fiber placement or splicing (Ellsworth and Joslin PONs)
  • Continued to evaluate which contractor to use for Blind Lake crossing (Bruin PON)
  • Began to pull fiber along 2.5 mile line on Boyce Road (Boyce PON)
  • Spliced 0 home drops (totals to date: 205 spliced – 89 in Werkner PON, 66 in Island Lake PON and 50 in Central Office PON)
  • Completed 7 new home self-installations on Roepke Road, Sandhill Pointe and South Lake Road in Central Office PON (totals to date: 185 with broadband – 87 in Werkner PON, 63 in Island Lake PON and 35 in Central Office PON)
Work to be completed 4/19/2020 through 4/25/2020:
  • Move forward with next steps for Blind Lake crossing (Bruin PON)
  • Continue H&M pedestal and hand hole tasks not related to fiber placement or splicing (Ellsworth and Joslin PONs)
  • Complete pulling remainder of fiber on Boyce Road (Boyce PON)
  • Begin to pull fiber in Wild Goose PON
  • Continue to reconfigure and/or repair splicing and pedestal prep in Central Office (east of M-52) PON
  • Continue to splice home drops in Central Office PON
  • Work with home owners on viable home self-installations
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (81) complete
Home Installations 40% (35) complete
88 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 3% (3) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation 16% complete
45 Subscribers

Bruin
Mainline Boring 97% complete (Blind Lake crossing)
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring 99% complete (Ellsworth Lake Road – pedestal installation and remaining road crossings)
90 Subscribers

Construction Update 4-5 to 4-18

Areas referenced below can be located on this map
Work completed 4/5/2020 through 4/11/2020:
  • Worked on H&M pedestal and hand holes tasks not related to fiber placement or splicing (Ellsworth PON)
  • Decided to use original contractor for Blind Lake crossing (Bruin PON)
  • Reconfigured and/or repaired 17 pedestals on Boyce Road and Coopersfield Road (Boyce PON)
  • Prepped 2.5 mile line on Boyce Road for cable
  • Spliced 10 home drops on Roepke Road and Sandhill Pointe in Central Office PON (totals to date: 195 spliced – 89 in Werkner PON, 66 in Island Lake PON and 50 in Central Office PON)
  • Completed 6 new home self-installations on Roe Road, Roepke Road, and South Lake Road in Central Office PON (totals to date: 172 with broadband – 87 in Werkner PON, 63 in Island Lake PON and 28 in Central Office PON)
Work to be completed 4/12/2020 through 4/18/2020:
  • Move forward with next steps for Blind Lake crossing (Bruin PON)
  • Continue H&M pedestal and hand hole tasks not related to fiber placement or splicing (Ellsworth PON)
  • Pull 2.5 miles of fiber on Boyce Road (Boyce PON)
  • Continue to reconfigure and/or repair splicing and pedestal prep in Central Office and Boyce PONs
  • Continue to splice home drops in Central Office PON
  • Work with home owners on viable home self-installations
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 94% (63) complete
(Note: Remaining 4 home installations are either not ready for service or additional drop work needed)
67 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 92% (81) complete
Home Installations 32% (28) complete
88 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
127 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 3% (3) complete
114 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation 16% complete
45 Subscribers

Bruin
Mainline Boring 97% complete (Blind Lake crossing)
52 Subscribers

Joslin
Mainline Boring complete
58 Subscribers

Ellsworth
Mainline Boring 98% complete (Ellsworth Lake Road – pedestal installation and remaining road crossings)
90 Subscribers

Public WiFi Access

To provide assistance to some Lyndon Township residents who do not yet have access to broadband, Lyndon Township, MEC, and your neighbors are working together on a unique solution to add public WiFi access to currently connected Lyndon Township homes. Residents who live close to someone who has been connected to broadband may be able to get online using a new “Lyndon Public” WiFi network.
On an opt-in basis, we are providing the capability for residents who have been connected to the broadband service to turn on a “Lyndon Public” WiFi guest network. Neighbors who are within range of these networks can connect with no password. Unfortunately WiFi only has a range of around 300 feet as a best case, so this will only help neighbors who live close to others who have the service, and only in the zones that are active – currently Werkner, Island Lake, and Central Office. Coverage will increase as additional households and zones come online. Please know that at long distances WiFi speeds may be slow and unreliable – for some residents this will be better than nothing, but please do not consider these long distance connections as a good example of what the fiber service is capable of.
We’d like to thank the residents who have chosen to opt in to this service and share their broadband connections. For connected residents who would still like to opt in, you can still do so opting in here. We’d also like to thank MEC for taking staff time during this busy period to make this happen.
If you have any questions please email lyndonbroadband1@gmail.com