Author Archives: Gary Munce
Construction Updates December 12 – January 11
- Staked 4,162 feet on Boyce Drive (Boyce PON)
- Three drill crews on-site
- Bored 1,952 feet on Island Lake Road (Island Lake PON)
- Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON)
- 3 pedestals and 2 handholes placed in Werkner PON
- Four drill crews on-site
- Continue boring on Island Lake Road (Island Lake PON)
- Continue boring on Werkner Road (Werkner PON)
- No flagging and minimal staking is expected for the week
Construction Updates December 15 – January 2
- Bored 208 feet at Lyndon Township Hall (Central Office PON)
- Received first pedestal order and installed first pedestals on Greystone Drive (Central Office PON)
- Bored 2,184 feet on Ellsworth Lake Road (Ellsworth PON)
- Attended December 11 pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
- Continue staking on private roads
- Three drill crews on-site
- Begin boring on Island Lake Road (Island Lake PON)
- Continue boring on Ellsworth Lake Road (Ellsworth PON)
- No field work planned
- Work to resume on January 3, 2019
Construction updates December 2-15
Areas referenced below can be located on this mapWork completed 12/2 through 12/8:
- Staked 1,645 feet on Hidden Lake Drive (Wild Goose PON)
- Staked 491 feet on Plourde Circle (Wild Goose PON)
- Bored 2,100 feet on Greystone Drive (Central Office PON)
- Signed and received permits from WCRC for first 12 roads
- Werkner Road
- Island Lake Road
- N Territorial Road
- Mester Road
- Waterloo Road (Werkner PON only)
- Island Lake Drive
- Lindley Road
- Rex Road
- Stofer Road
- Roe Road
- Jaycox Road
- Farnsworth Road
- Met with snake expert for introductions and prioritized work activities
- Placed first fiber order
- Placed first pedestal order
- Validated process for Notice to Proceed by road for wetland areas and Tier 1 snake habitat
Work to be completed 12/9 through 12/15:
- Continue staking on private roads
- Two drill crews on-site
- Bore remaining 100 feet on Stoney Ridge Road (Werkner PON)
- Complete boring on Greystone Drive (Central Office PON) and place first pedestals
- Begin boring on Ellsworth Lake Road (Ellsworth PON)
- Begin boring on Werkner Road (Werkner PON)
- Begin boring on Island Lake Road (Island Lake PON)
- Attend pre-construction meeting with Washtenaw County Road Commission, H&M and Lyndon Township
- Begin snake field work
- Continue to flag wetlands ahead of boring activities
- Receive first pedestal order
Monthly Construction Updates
__________________________
- Continue staking on private roads
- Two drill crews on-site
- Bore remaining 100 feet on Stoney Ridge Road (Werkner Zone)
- Complete boring on Greystone Drive (Central Office Zone)
- Begin boring on Ellsworth Lake Road (Ellsworth Zone)
- Sign and obtain permits from WCRC for first 12 roads
- Werkner Road
- Island Lake Road
- N Territorial Road
- Mester Road
- Waterloo Road (Werkner PON only)
- Island Lake Drive
- Lindley Road
- Rex Road
- Stofer Road
- Roe Road
- Jaycox Road
- Farnsworth Road
- Bored 548 feet on Stoney Ridge Road (Werkner Zone)
- Bored 1,585 feet on Graystone Drive (Central Office Zone)
- Staked 1,354 feet on Wildflower Ridge (Werkner Zone)
- Staked 829 feet on Bens Drive (Sugarloaf Zone)
- Staked 1,672 feet on Coopersfield Road (Boyce Zone)
- Submitted WCRC permit applications for the following roads:
- Bowdish Road
- Boyce Road
- Clark Lake Road
- Lingane Road
- Oakridge Road
- Westbourne Court
- Beeman Road
- Bush Road
- Gaddis Road
- Osius Road
- Guinan Drive
Middle Mile Work Begins on M-52
Work has begun on M-52 to bring Middle Mile Fiber to Lyndon Township. Middle mile fiber is that section of fiber that connects a network (Lyndon) to the greater world of the internet.
Midwest Energy and Communications (MEC), the Internet Service Provider for Lyndon Township is overseeing this work which is the result of a creative and unique partnership between the Chelsea School District, MEC and Lyndon Township. This fiber will connect to the Chelsea School District Network and extend to Lyndon fiber at Werkner Road. To learn more about the partnership:
Here is that work in pictures.
Partnership with Chelsea School District moves Lyndon project Forward
The Chelsea School District, Midwest Energy and Communications and Lyndon Township have formed a creative and mutually beneficial partnership that will help move the Lyndon Broadband Project forward.
Eead more about the partnership.
Construction Update November 30 2018
Staking completed:
Central Office zone (Greystone Drive), Long Lake zone (Chestnut Lane, Hickory Lane, Stonehill Drive, Bauer Court), Sugarloaf zone (Sugarloaf Lake Road (partial), Cedar Drive), Ellsworth zone (Ellsworth Lake Road (partial), Roepke Court, Medina Drive)
776 feet bored and conduit placed in ground on Stoney Ridge Road (Werkner Zone)
30 reels of duct received at Canton warehouse
Staking to continue on private roads. Staking and construction may be experience temporary delays due to unforeseen conditions.
First batch of fiber to be ordered
Two drill crews on site to finish boring on Stoney Ridge Road (Werkner zone) and Greystone Drive (Central Office zone)
Permits are expected for the following WCRC roads:
Werkner Road
Island Lake Road
N Territorial Road
Mester Road
Waterloo Road
Island Lake Drive
Lindley Road
Rex Road
Stofer Road
Roe Road
Jaycox Road
Farnsworth Road
Permit applications to be submitted for another 10 WCRC roads
Additional Drilling to begin week of November 12
Beginning the week of November 12, Henkels and McCoy will begin construction on the private roads that have been staked in the Werkner Zone (Stoney Ridge Road) and Island Lake Zone (Beede Drive, South Drive).
A map of the zones in the township can be found at:
It is important to be aware that construction crews will now be actively working on the Township public and private roadways. We encourage everyone to exercise caution while driving on our roadways. In addition, it is also important to remember that these construction sites are subject to strict safety regulations that require safety vest, hard hat and safety glasses for anyone on site.
Drilling to begin on Broadband Project
On Monday, November 12, drilling will begin along M-52 to bring the main line fiber to Lyndon Township. The drilling will take place along a one mile stretch south of the roundabout at Werkner Road. The fiber will enter Lyndon Township on Werkner Road just east of M-52. Later this month drilling will commence from that location to complete the main line fiber connection to the Lyndon Township Hall via Werkner Road, Island Lake Road and North Territorial Road. At the same time, work will begin on building out fiber lines in Werkner and Island Lake zones.
A map of the zones in the township can be found at:
It is important to be aware that construction crews will now be actively working on the Township public and private roadways. We encourage everyone to exercise caution while driving on our roadways. In addition, it is also important to remember that these construction sites are subject to strict safety regulations that require safety vest, hard hat and safety glasses for anyone on site.