Work completed 3/10 through 3/16:
- 3 crews on-site
- Bored 815 feet on Werkner Road (Werkner PON)
- Bored 1,537 feet on Werkner Road (Island Lake PON)
- Bored 420 feet on N Territorial (Central Office PON)
- Lyndon Township, H&M and MEC drop contractors attended Future Path (for drops around lakes) training
- Developed materials for Eastern Massassagua Rattlesnake training
- Finalized plans and marketing for March 27 Open House with MEC at Lyndon Township Hall. MEC staff will be there from 3:00 pm to 6:00 pm. From 6:00 pm to 7:00 pm there will be an education session on The Drop Installation Process: This is a key step in the process as build the service drop to your home. Learn how to prepare for this step, what happens on your property, and what follows.
- 633 total sign-ups
Work to be completed 3/17 through 3/23:
- 3 to 4 crews on-site
- Continue boring on Werkner Road and N Territorial Road
- Work on road crossings and tying in lines for completed borings
- Obtain additional details regarding splicing
- Order first batch of tracer wire
- Finalize arrangements for equipment staging area in Lyndon Township
- Provide Massassagua Rattlesnake training to existing and incoming crews
- Schedule in-person Broadband Implementation Committee meeting