Construction Updates December 12 – January 11

Areas referenced below can be located on this map
Work completed 12/16 through 1/4:
  • Staked 4,162 feet on Boyce Drive (Boyce PON)
  • Three drill crews on-site
  • Bored 1,952 feet on Island Lake Road (Island Lake PON)
  • Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON)
  • 3 pedestals and 2 handholes placed in Werkner PON
Work to be completed 1/7 through 1/11:
  • Four drill crews on-site
  • Continue boring on Island Lake Road (Island Lake PON)
  • Continue boring on Werkner Road (Werkner PON)
  • No flagging and minimal staking is expected for the week

 

Posted in Uncategorized, Updates.