- Spliced in Bruin and Joslin PONs
- Continued restoration activities
- Installed 12 home drops in Island Lake and Wild Goose PONs (totals to date: 671 drops – 93 in Werkner PON, 70 in Island Lake PON, 87 in Central Office PON, 128 in Boyce PON, 119 in Sugarloaf PON, 43 in Guinan PON, 82 in Long Lake PON and 49 in Wild Goose PON).
- Spliced 21 home drops in Wild Goose PON (totals to date: 627 spliced – 93 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 127 in Boyce PON, 107 in Sugarloaf PON, 42 in Guinan PON, 81 in Long Lake PON, and 23 in Wild Goose PON).
- Completed 14 new home installations in Werkner, Island Lake, Sugarloaf, and Long Lake PONs (totals to date: 559 with broadband – 91 in Werkner PON, 67 in Island Lake PON, 83 in Central Office PON, 120 in Boyce PON, 101 in Sugarloaf PON, 37 in Guinan PON and 60 in Long Lake PON).
- Continue splicing in Bruin and Joslin PONs
- Begin to install home drops in Bruin PON
- Continue home drop splicing in Sugarloaf and Wild Goose PONs
- Continue home installations in Central Office, Boyce, Sugarloaf, Guinan and Long Lake PONs
- Continue restoration activities
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (93) complete
Home Installations 98% (91) complete
93 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 96% (67) complete
70 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 93% (83) complete
89 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (128) complete
Home Installations 92% (120) complete
131 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (119) complete
Home Installations 85% (101) complete
119 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 86% (37) complete
43 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (82) complete
Home Installations 73% (60) complete
82 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (49) complete
Home Installations begin early September
49 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-August
Home Installations begin late September
56 Subscribers
Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late August
Home Installations begin early October
66 Subscribers
Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin mid-October
91 Subscribers