- Replaced and spliced fiber on Sugarloaf Lake Road in Sugarloaf PON
- Completed pulling fiber and installing hand holes in Bruin PON – except for Blind Lake crossing
- Prepped for Blind Lake crossing
- Began to pull fiber in Joslin PON
- Continued splicing in Sugarloaf PON
- Finished splicing drops in Central Office PON
- Installed 11 home drops (totals to date: 404 drops – 89 in Werkner PON, 67 in Island Lake PON, 86 in Central Office PON, 127 in Boyce PON, 23 in Sugarloaf PON and 12 in Long Lake PON).
- Spliced 33 home drops (totals to date: 330 spliced – 89 in Werkner PON, 66 in Island Lake PON, 86 in Central Office PON and 89 in Boyce PON)
- Completed 9 new home installations (totals to date: 220 with broadband – 87 in Werkner PON, 64 in Island Lake PON, 61 in Central Office PON and 8 in Boyce PON)
- Schedule restoration activities
- Rescheduled Blind Lake crossing for week of June 1 due to this week’s inclement weather
- Continue to pull fiber in Joslin PON
- Continue home drops in Long Lake and Sugarloaf Lake PONs
- Continue to splice home drops in Boyce PON
- Continue home installations in Central Office and Boyce PONs
- Mainline Boring
- Mainline Fiber Installation
- Drop Installation (bringing fiber cable from the road to the side of each home)
- Home Installation (bringing fiber into you home and attaching to network router)
Here is the current status for zones or PONS that are in progress.
Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 98% (87) complete
(Note: Remaining 2 home installations are not ready for service)
89 Subscribers
Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 96% (64) complete
(Note: Remaining 2 home installations are not ready for service)
67 Subscribers
Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 71% (61) complete
86 Subscribers
Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 6% (8)
127 Subscribers
Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 20% (23) complete
114 Subscribers
Guinan
Mainline Boring complete
Mainline Fiber Installation complete
40 Subscribers
Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 6% (5) complete
80 Subscribers
Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
45 Subscribers
Bruin
Mainline Boring complete
Mainline Fiber Installation 97% complete
52 Subscribers
Joslin
Mainline Boring complete
58 Subscribers
Ellsworth
Mainline Boring complete
90 Subscribers