Construction Update 10-25 to 11-7

Areas referenced below can be located on this map
Work completed 10/25/2020 through 10/31/2020:
  • Installed 6 home drops in Island Lake, Sugarloaf, Joslin and Ellsworth PONs (totals to date: 906 drops – 96 in Werkner PON, 76 in Island Lake PON, 85 in Central Office PON, 128 in Boyce PON, 123 in Sugarloaf PON, 42 in Guinan PON, 84 in Long Lake PON, 47 in Wild Goose PON, 54 in Bruin PON, 75 in Joslin PON and 96 in Ellsworth PON).
  • Spliced 96 home drops in Sugarloaf, Wild Goose, Joslin and Ellsworth PONs (totals to date: 899 spliced – 96 in Werkner PON, 75 in Island Lake PON, 85 in Central Office PON, 128 in Boyce PON, 122 in Sugarloaf PON, 42 in Guinan PON, 84 in Long Lake PON, 47 in Wild Goose PON, 54 in Bruin PON, 74 in Joslin PON and 92 in Ellsworth PON).
  • Began home installations in Ellsworth PON
  • Completed 43 new home installations in Werkner, Island Lake, Boyce, Sugarloaf, Guinan, Wild Goose, Bruin, Joslin and Ellsworth PONs (totals to date: 805 with broadband – 96 in Werkner PON, 75 in Island Lake PON, 85 in Central Office PON, 127 in Boyce PON, 122 in Sugarloaf PON, 42 in Guinan PON, 83 in Long Lake PON, 46 in Wild Goose PON, 53 in Bruin PON, 57 in Joslin PON, and 19 in Ellsworth PON).
  • Note:  With the drops being completed last week, an evaluation of the addresses that have not requested home installations was implemented.  A total of 23 homes had requested drops but either canceled their installations or postponed their home installation until the spring.  The drop, splice and home installation numbers noted above reflect this change.
Work to be completed 11/1/2020 through 11/7/2020:
  • Continue home installations in Joslin and Ellsworth PONs
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (96) complete
Home Installations 100% (96) complete
96 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (76) complete
Home Installations 99% (75) complete
76 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (85) complete
Home Installations 100% (85) complete
85 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (128) complete
Home Installations 99% (127) complete
128 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (123) complete
Home Installations 99% (122) complete
123 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (42) complete
Home Installations 100% (42) complete
42 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (84) complete
Home Installations 99% (83) complete
84 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (47) complete
Home Installations 98% (46) complete
47 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (54) complete
Home Installations 98% (53) complete
54 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (75) complete
Home Installations 76% (57) complete
75 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (96) complete
Home Installations 20% (19) complete
96 Subscribers