Construction Update 8-16 to 8-29

Areas referenced below can be located on this map
Work completed 8/16/2020 through 8/22/2020:
  • Completed splicing in Bruin PON
  • Continue splicing in Joslin PON
  • Continued restoration activities
  • Began home drops in Bruin PON
  • Installed 21 home drops in Boyce, Sugarloaf, Long Lake, Wild Goose and Bruin PONs (totals to date: 692 drops – 93 in Werkner PON, 70 in Island Lake PON, 87 in Central Office PON, 130 in Boyce PON, 120 in Sugarloaf PON, 43 in Guinan PON, 83 in Long Lake PON, 51 in Wild Goose PON and 15 in Bruin PON).
  • Spliced 20 home drops in Boyce, Sugarloaf, and Wild Goose PONs (totals to date: 647 spliced – 93 in Werkner PON, 67 in Island Lake PON, 87 in Central Office PON, 128 in Boyce PON, 111 in Sugarloaf PON, 42 in Guinan PON, 81 in Long Lake PON, and 38 in Wild Goose PON).
  • Completed 12 new home installations in Werkner, Central Office, Boyce, Sugarloaf, Guinan, Long Lake and Wild Goose PONs (totals to date: 571 with broadband – 92 in Werkner PON, 67 in Island Lake PON, 84 in Central Office PON, 122 in Boyce PON, 103 in Sugarloaf PON, 38 in Guinan PON, 63 in Long Lake PON, and 2 in Wild Goose PON).
Work to be completed 8/23/2020 through 8/29/2020:
  • Continue splicing in Joslin PON
  • Continue to install home drops in Bruin PON
  • Continue home drop splicing in Sugarloaf and Wild Goose PONs
  • Continue home installations in Central Office, Boyce, Sugarloaf,  Guinan, Long Lake and Wild Goose PONs
  • Continue restoration activities
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.  

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (93) complete
Home Installations 99% (92) complete
93 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (70) complete
Home Installations 96% (67) complete
70 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 98% (87) complete
Home Installations 94% (84) complete
89 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 99% (130) complete
Home Installations 93% (122) complete
131 Subscribers

Sugarloaf
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (120) complete
Home Installations 86% (103) complete
120 Subscribers

Guinan
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (43) complete
Home Installations 88% (38) complete
43 Subscribers

Long Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installation 100% (83) complete
Home Installations 76% (63) complete
83 Subscribers

Wild Goose
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 100% (51) complete
Home Installations 4% (2) complete
Note:  Home installations were scheduled to begin in early September and have already begun.
51 Subscribers

Bruin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 27% (15) complete
Home Installations begin late September
56 Subscribers

Joslin
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin late August
Home Installations begin early October
66 Subscribers

Ellsworth
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations begin mid-September
Home Installations begin mid-October
91 Subscribers