Construction Update1-12 to 1-25

Areas referenced below can be located on this map
Work completed 1/12/2020 through 1/18/2020:
  • 4 to 8 bore crews on-site plus one fiber pulling crew
  • Bored 100 feet on Sugarloaf Lake Road (Sugarloaf PON)
  • Bored 750 feet on Bruin Lake Road (Bruin PON)
  • Bored 365 feet on Bruin Lake Shores (Bruin PON)
  • Bored 2,223 feet on Blind Lake Road (Bruin PON)
  • Bored 8,713 feet on Joslin Lake Road (Joslin PON)
  • Bored 2,096 feet on Farnsworth Road (Ellsworth PON)
  • Bored 1,528 feet on Roepke Road (Ellsworth PON)
  • Bored 3,545 feet on Jaycox Road (Ellsworth)
  • Bored 550 feet on Bowdish Road (Ellsworth)
  • Installed 3 pedestals in Sugarloaf PON and 9 pedestals in Bruin PON
  • Pulled 3,312 feet of fiber in Sugarloaf PON
  • Completed 12 new drops (totals to-date: 364 total drops – 89 in Werkner PON, 68 in Island Lake PON, 79 in Central Office PON, 126 in Boyce PON and 2 in Sugarloaf PON). Note: Drops are finished until Spring 2020.
  • Spliced 0 job (totals to-date: 150 spliced – 84 in Werkner PON, 65 in Island Lake PON and 1 in Central Office PON).
  • 1 new home installation (totals to date: 142 with broadband – 79 in Werkner PON, 62 in Island Lake PON, and 1 in Central Office PON (Township Hall)).
Work to be completed 1/19/2020 through 1/25/2020:
  • 8 bore crews on-site
  • Bore on Bruin Lake Road (Bruin PON)
  • Bore on Bruin Lake Shores (Bruin PON)
  • Bore on Joslin Lake Road (Bruin PON)
  • Bore on Blind Lake Road (Bruin PON)
  • Homewild Drive (Joslin PON)
  • Bore on Roepke Road (Ellsworth PON)
  • Bore on Jaycox Road (Ellsworth PON)
  • Bore on Bowdish Road (Ellsworth PON)
There are four basic phases of work in bringing internet service to your home:
  • Mainline Boring
  • Mainline Fiber Installation
  • Drop Installation (bringing fiber cable from the road to the side of each home)
  • Home Installation (bringing fiber into you home and attaching to network router)

Here is the current status for zones or PONS that are in progress.

Werkner
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 89% (79) complete
89 Subscribers

Island Lake
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations complete
Home Installations 91% (62) complete
68 Subscribers

Central Office
Mainline Boring complete
Mainline Fiber Installation complete
Drop Installations 90% (79) complete
Home Installations 1% (1) complete
86 Subscribers

Boyce
Mainline Boring complete
Mainline Fiber Installation 99% complete
Drop Installations complete
126 Subscribers

Sugarloaf
Mainline Boring 99% complete
Mainline Fiber Installation 99% complete
Drop Installation 2% (2) complete
114 Subscribers

Guinan
Mainline Boring 89% complete
Mainline Fiber Installation 49% complete
40 Subscribers

Long Lake
Mainline Boring 96% complete
Mainline Fiber Installation 64% complete
80 Subscribers

Wild Goose
Mainline Boring 84% complete
Mainline Fiber Installation 24% complete
45 Subscribers

Bruin
Mainline Boring 55% complete
52 Subscribers

Joslin
Mainline Boring 42% complete
58 Subscribers

Ellsworth
Mainline Boring 52% complete
90 Subscribers

Posted in Uncategorized, Updates.