Construction Update 9-1 to 9-14

Areas referenced below can be located on this map

Work completed 9/1 through 9/7:
  • 5 to 7 bore crews on-site plus one fiber pulling crew and one splicing crew
  • Bored 120 feet on M-52 (Boyce PON)
  • Bored 253 feet on N Territorial (Central Office PON)
  • Bored 1,674 feet on Boyce Road (Boyce PON)
  • Bored 1,265 feet on Boyce Road (Ellsworth PON)
  • Bored 1,858 feet on Roe Road (Sugarloaf PON)
  • Bored 1,962 feet on Osius Road (Sugarloaf PON)
  • Pulled 3,070 feet of fiber in the Island Lake PON
  • Continued splicing in Island Lake PON
  • One new sign-up (833 total; 308 basic, 278 ultra, 240 gig, 4 undecided, 170 with phone, 3 phone only)
  • Broadband was lit in two houses this week (16 houses have broadband to-date)
  • No new drops this week (totals to-date: 46 total drops – 28 in Werkner PON and 18 in Island Lake PON)
Work to be completed 9/8 through 9/14:
  • 7 bore crews on-site plus a fiber pull and splicing crew
  • Bore on M-52 (Central Office PON)
  • Bore on Boyce Road (Boyce and Ellsworth PON)
  • Bore on Osius Road (Sugarloaf PON)
  • Bore on Waterloo Road (Sugarloaf PON)
  • Begin to pull and splice fiber in Central Office PON
  • Resume drop installations in Werkner and Island Lake PONs
  • Release Island Lake PON to MEC to begin drops and installations