Construction Update 6-16 to 6-29

Areas referenced below can be located on this map
LYNDON DESIGN 110518

Work completed 6/16 through 6/22:
  • 5 bore crews on-site
  • Bored 118 feet on Mester Road (Werkner PON)
  • Bored 207 feet on Cooper Ridge Drive / Waterloo Road connector (Werkner PON)
  • Bored 520 feet on Island Lake Drive (Island Lake PON)
  • Bored 3,310 feet on North Territorial Road (Island Lake PON)
  • Bored 477 feet on Roepke Road (Central Office PON)
  • Bored 2,294 feet on Coopersfield Road (Boyce PON)
  • Installed 1 pedestal in Werkner PON, 5 pedestals in Boyce PON, and 7 pedestals in Island Lake PON
  • Hired new splicers
  • No new signups
Work to be completed 6/23 through 6/29:
  • 5 bore crews on-site
  • Finish boring on Cooper Ridge Drive / Waterloo Road Connector (Werkner PON)
  • Bore under Island Lake (Island Lake PON)
  • Bore on N. Territorial Road (Island Lake PON)
  • Bore on Roepke Road (Central Office PON)
  • Bore on Coopersfield Road (Boyce PON)
  • Splice along Waterloo Road
  • Splice into house box, install router, and activate broadband service at 5 beta testers on Werkner Road