Work completed 6/16 through 6/22:
- 5 bore crews on-site
- Bored 118 feet on Mester Road (Werkner PON)
- Bored 207 feet on Cooper Ridge Drive / Waterloo Road connector (Werkner PON)
- Bored 520 feet on Island Lake Drive (Island Lake PON)
- Bored 3,310 feet on North Territorial Road (Island Lake PON)
- Bored 477 feet on Roepke Road (Central Office PON)
- Bored 2,294 feet on Coopersfield Road (Boyce PON)
- Installed 1 pedestal in Werkner PON, 5 pedestals in Boyce PON, and 7 pedestals in Island Lake PON
- Hired new splicers
- No new signups
Work to be completed 6/23 through 6/29:
- 5 bore crews on-site
- Finish boring on Cooper Ridge Drive / Waterloo Road Connector (Werkner PON)
- Bore under Island Lake (Island Lake PON)
- Bore on N. Territorial Road (Island Lake PON)
- Bore on Roepke Road (Central Office PON)
- Bore on Coopersfield Road (Boyce PON)
- Splice along Waterloo Road
- Splice into house box, install router, and activate broadband service at 5 beta testers on Werkner Road