Work completed 12/16 through 1/4:
- Staked 4,162 feet on Boyce Drive (Boyce PON)
- Three drill crews on-site
- Bored 1,952 feet on Island Lake Road (Island Lake PON)
- Completed boring 3,469 feet on Ellsworth Lake Road (Ellsworth PON)
- 3 pedestals and 2 handholes placed in Werkner PON
Work to be completed 1/7 through 1/11:
- Four drill crews on-site
- Continue boring on Island Lake Road (Island Lake PON)
- Continue boring on Werkner Road (Werkner PON)
- No flagging and minimal staking is expected for the week