Monthly Construction Updates

Midwest Energy and Communications (MEC), our Internet Service Provider, will begin  posting monthly construction updates on their website as well as emailing these updates to everyone who has subscribed to the broadband service.  The first of these updates is included below.
We will post these updates here as well and continue to post other information that may become available during the month.
__________________________
Lyndon Township Construction Update: December 2018
After a lot of hard work evaluating and awarding bids, and working with many state and local agencies for permits, Lyndon Township began construction for the high-speed fiber internet project. In fact, folks on Stoney Ridge Road and Greystone Drive already are seeing crews install conduit for the fiber. Those crews soon will move to Wildflower Ridge, Bens Drive, and Coopersfield Road.
Mother Nature is really in control as we move forward. With a mild winter, construction can continue uninterrupted, and we can begin home installations in the southeast part of the township by spring.  Keeping to that schedule, we’ll have all interested subscribers hooked up by the end of 2019.
It’s hard to be patient when you’ve waited so long for a high-speed solution, but the process is now underway and we promise it will be worth the wait. If you have friends, family or neighbors within the township who have not yet signed up, please encourage them to visit www.teammidwest.com/lyndon before April 30 to take advantage of the free installation.
We’re honored to be your internet service provider and look forward to bringing high-speed fiber internet to Lyndon
_____________________
Additional construction updates
Work to be completed 12/2 through 12/8:
  • Continue staking on private roads
  • Two drill crews on-site
  • Bore remaining 100 feet on Stoney Ridge Road (Werkner Zone)
  • Complete boring on Greystone Drive (Central Office Zone)
  • Begin boring on Ellsworth Lake Road (Ellsworth Zone)
  • Sign and obtain permits from WCRC for first 12 roads
    • Werkner Road
    • Island Lake Road
    • N Territorial Road
    • Mester Road
    • Waterloo Road (Werkner PON only)
    • Island Lake Drive
    • Lindley Road
    • Rex Road
    • Stofer Road
    • Roe Road
    • Jaycox Road
    • Farnsworth Road
Work completed 11/26 through 12/1:
  • Bored 548 feet on Stoney Ridge Road (Werkner Zone)
  • Bored 1,585 feet on Graystone Drive (Central Office Zone)
  • Staked 1,354 feet on Wildflower Ridge (Werkner Zone)
  • Staked 829 feet on Bens Drive (Sugarloaf Zone)
  • Staked 1,672 feet on Coopersfield Road (Boyce Zone)
  • Submitted WCRC permit applications for the following roads:
    • Bowdish Road
    • Boyce Road
    • Clark Lake Road
    • Lingane Road
    • Oakridge Road
    • Westbourne Court
    • Beeman Road
    • Bush Road
    • Gaddis Road
    • Osius Road
    • Guinan Drive
Posted in Updates.